200 A service, 12 kW generator
The standard standby installation, and the surprising answer.
200 A switch — sized on the service, not the 50 A the generator makes
What size transfer switch you need — and why a whole-house switch is rated on your service rather than on the generator, which is the opposite of what most people expect.
This is the decision that sets the price. Whole-house follows the service.
The main breaker. A whole-house switch must match it.
Running, not surge. This sizes the generator conductors, not the switch.
Feet. Voltage drop matters more on generator power.
A whole-house switch sits in the service conductors, so it is rated on the SERVICE, not the generator — 200 A here. A 200 A service with a 10 kW generator still needs a 200 A switch, because utility power flows through the switch too and it must carry whatever the service conductors can.
200 A switch, from the UL 1008 standard sizes. Note how coarse those are — 100, 150, 200, 400 — so rounding up frequently lands somewhere considerably more expensive than the next breaker size would.
The generator supplies 50.0 A at 240 V (12,000 W running). That figure sizes the generator CONDUCTORS and the generator breaker — not the switch.
The generator covers about 25% of the service rating, so the switch is far larger than the generator can actually feed. That is normal and correct — but it means load management or manual discipline is what stops the generator being overloaded, not the switch.
Generator conductors: NEC 445.13 requires at least 115% of the nameplate rating, and 125% is the usual practice — 62.5 A, so 6 AWG copper.
A whole-house switch is usually SERVICE-RATED, meaning it contains the service disconnect and neutral-to-ground bond and replaces the main breaker position. A non-service-rated switch has to sit downstream of an existing disconnect. The two are not interchangeable and the difference is visible on the label, not in the box.
The switch must break the neutral only where the generator is a separately derived system — a portable generator with a bonded neutral. Getting this wrong either leaves two neutral-to-ground bonds in the system or none, and both are hazards. Check whether your generator’s neutral is bonded before choosing.
Over 30 ft, check voltage drop on the generator feeder as well as ampacity — a generator has no utility stiffness behind it, so drop shows up as poor motor starting rather than as a dim light.
The standard standby installation, and the surprising answer.
200 A switch — sized on the service, not the 50 A the generator makes
A partial-load switch is a fraction of the size and the price.
50 A switch for the same generator
Fridge, furnace, a few lights. The common manual-switch case.
30 A switch
Where whole-house switches get expensive fast.
400 A switch for a generator making 92 A
When to use this: specifying a standby installation, or checking a quote that seems to have the wrong size switch in it.
The answer most people expect is that a 10 kW generator needs a switch rated for 10 kW. For a whole-house switch that is wrong, and the reason is simple once stated:
A whole-house switch sits in the service conductors. In normal operation the entire house load flows through it from the utility. It therefore has to be rated for whatever the service can deliver — 200 A on a 200 A service, regardless of whether the generator behind it makes 50 A or 90 A.
| Whole house | Selected circuits | |
|---|---|---|
| Sized on | The service rating | The transferred load × 125% |
| Sits | In the service conductors | Downstream, on a subpanel |
| 200 A service, 12 kW generator | 200 A switch | 50 A switch |
| Overload protection | Load management or discipline | Inherent — only chosen circuits transfer |
The choice between them is the first decision, not the last, because it sets both the size and most of the cost. A partial-load switch for the same generator is frequently a quarter of the price.
Not the switch. A 200 A switch will happily pass more than a 12 kW generator can make. On a whole-house installation the protection is either a load management system that sheds circuits automatically, or the discipline not to run the range, dryer and air conditioning together. Where a generator is undersized relative to the service, that is worth being explicit about rather than discovering during an outage.
UL 1008 transfer switches come in far fewer sizes than circuit breakers: 30, 50, 60, 100, 150, 200, 400, 600, 800, 1000 amps. Note the jump from 200 straight to 400 — a 225 A requirement rounds up to 400 A with nothing in between.
It is worth checking your figure against those steps before assuming a slightly larger service is a small upgrade. Going from a 200 A to a 225 A service can double the switch cost.
The generator rating sizes the conductors and breaker between the generator and the switch — a different calculation on the other side of the same box.
| Generator | Output at 240 V | Conductors at 125% |
|---|---|---|
| 5.5 kW | 22.9 A | 28.6 A |
| 7.5 kW | 31.3 A | 39.1 A |
| 10.0 kW | 41.7 A | 52.1 A |
| 12.0 kW | 50.0 A | 62.5 A |
| 16.0 kW | 66.7 A | 83.3 A |
| 22.0 kW | 91.7 A | 114.6 A |
| 26.0 kW | 108.3 A | 135.4 A |
NEC 445.13 requires generator conductors rated at least 115% of the nameplate; 125% is normal practice. Check voltage drop on the run too — a generator has no utility stiffness behind it, so drop shows up as poor motor starting rather than as a dim light. Our wire size calculator handles both.
A service-rated switch contains the service disconnecting means and the neutral-to-ground bond, and replaces the main breaker position. A standard switch must sit downstream of an existing service disconnect.
They are not interchangeable. Fitting a non-service-rated switch as the service disconnect leaves the installation without a compliant disconnect; fitting a service-rated one downstream creates a second neutral-to-ground bond. Both are inspection failures and neither is visible without reading the label.
Whether the switch should break the neutral depends on whether the generator is a separately derived system, which depends on whether its neutral is bonded to its frame.
Portable generators are commonly bonded; standby units are commonly floating. Check yours before ordering the switch — this is not something that can be corrected afterwards without replacing hardware.
Back-feeding through a dryer or range outlet with a double-male cord. It energises the utility conductors outside the house and can kill a lineworker restoring power. It is illegal essentially everywhere, and a manual transfer switch or an interlock kit — both entirely compliant under NEC 702 — costs very little by comparison.
Sizing the generator itself is a separate question, and the surge behaviour matters more than the running load: our generator sizing calculator covers that.
This decision sets the size and most of the cost. A whole-house switch sits in the service conductors; a partial switch carries only what it transfers.
The switch carries utility power too, so it must be rated for whatever the service conductors can deliver — regardless of how small the generator is.
Standby load is treated as continuous, because an outage is not a three-hour event.
From the generator output at 125%. NEC 445.13 requires at least 115% of the nameplate rating.
Whether the switch breaks the neutral depends on whether the generator is a separately derived system, which depends on whether its neutral is bonded.
For a whole-house switch, the same rating as your service — a 200 A service takes a 200 A switch, whatever size the generator is. For a switch covering selected circuits, size on the load being transferred at 125%: 7,500 W at 240 V is 39 A, so a 50 A switch. The whole-house answer surprises people, and it is the more expensive one.
Because a whole-house switch sits in the service conductors and carries utility power as well as generator power. In normal operation the entire house load flows through it from the grid, so it must be rated for whatever the service can deliver. The generator rating sizes the generator conductors and the generator breaker — two different things on the other side of the switch.
A service-rated switch contains the service disconnecting means and the neutral-to-ground bond, and it replaces the main breaker position. A standard switch must sit downstream of an existing service disconnect. They are not interchangeable: fitting a non-service-rated switch as the service disconnect leaves the installation without a compliant disconnect, and fitting a service-rated one downstream can create a second neutral-to-ground bond.
It depends on whether the generator is a separately derived system, which comes down to whether its neutral is bonded to its frame. A generator with a bonded neutral is separately derived and needs a switch that breaks the neutral; one with a floating neutral is not, and must not have its neutral switched. Getting this wrong leaves the system with either two neutral-to-ground bonds or none — both hazardous, and both invisible until something faults.
It can be connected to a whole-house switch, but it cannot supply the whole house at once. A 10 kW generator makes about 42 A at 240 V against a 200 A service. What stops it being overloaded is load management — either a device that sheds circuits automatically, or the discipline not to run the range and the dryer together. The switch does not protect the generator from that.
NEC 445.13 requires generator conductors rated at least 115% of the nameplate current, and 125% is normal practice. A 12 kW generator at 240 V produces 50 A, so 62.5 A of conductor — 6 AWG copper. Check voltage drop on the run as well: a generator has no utility stiffness behind it, so drop shows up as poor motor starting rather than as a dim light.
UL 1008 switches are made in far fewer sizes than circuit breakers — 30, 50, 60, 100, 150, 200, then straight to 400. A 225 A requirement rounds up to 400 A with nothing between, which is a large jump in cost. It is worth checking your calculated figure against those steps before assuming a slightly larger service is a small upgrade.
Yes, and NEC 702 covers both manual and automatic optional standby systems. A manual switch or an interlock kit is considerably cheaper and entirely compliant. What is never acceptable is back-feeding through a dryer outlet without a transfer means — that energises the utility lines outside the house and can kill a lineworker.

Technical reviewer
Electrician · 10+ years of installation work in Bangladesh and the wider South Asian region
He reads the result the way an installer would: are the defaults values people actually meet, does the warning fire where you would stop and think, and is the answer something you could buy and fit? The code figures themselves come from the published standards cited below, not from him — that boundary is set out on his profile.
The full process is written up in the methodology and editorial policy. Results are engineering guidance, not a code sign-off — see the disclaimer. If a result looks wrong, tell us; corrections are answered before anything else.
What size generator you actually need — running watts plus the largest single starting surge, derated for altitude and heat. Not the sum of every surge, which is how most calculators oversize you.
⚡Whether your existing panel has room for a new circuit — in amps and in breaker spaces, which are different constraints and only one of them is visible through the door.
kVASize a house service the way an electrician does: NEC Article 220 standard calculation, with the demand factors that stop a 40 kW house needing a 400 A service.
AWGWhat size wire you need, from the load, the run length and the conditions — sized against both NEC ampacity and voltage drop, with the terminal temperature rule that stops 90 °C wire giving 90 °C ampacity.